South of Staten Island, 2,400 linear feet of breakwaters are reducing storm risk, growing #marine habitat and saving roughly USD 14 million in mitigation fees.

Living Breakwaters is a USD 111 million coastal resiliency project off Tottenville, Staten Island. It started in HUD’s Rebuild by Design competition after Hurricane Sandy and was delivered for New York State Homes and Community Renewal. 

ECOncrete worked on a multidisciplinary team led by SCAPE, with WSP, Arcadis, COWI, and MFS Engineers. Completed in 2024, Living Breakwaters is now widely considered a model for nature-based infrastructure.

𝗛𝗲𝗿𝗲’𝘀 𝗵𝗼𝘄 𝘁𝗵𝗲 𝗽𝗿𝗼𝗷𝗲𝗰𝘁 𝗰𝗮𝗺𝗲 𝘁𝗼𝗴𝗲𝘁𝗵𝗲𝗿:

🔹 Hurricane Sandy left Tottenville exposed to wave energy and erosion.

🔹 The team designed near-shore breakwaters to reduce storm risk and restore habitat, with hydrodynamic modeling and physical testing informing the design.

🔹 ECOncrete armor units and tide pools were integrated into the breakwaters, resulting in the formation of “reef ridges” and “reef streets” that support native species such as oysters and mussels.

🔹 The ECOncrete units fit standard precast and marine construction practices, so the habitat features added no extra construction steps.

𝗛𝗮𝗯𝗶𝘁𝗮𝘁 𝗯𝘂𝗶𝗹𝘁 𝗶𝗻, 𝗺𝗶𝘁𝗶𝗴𝗮𝘁𝗶𝗼𝗻 𝗰𝗼𝘀𝘁𝘀 𝗰𝘂𝘁

By factoring habitat into the breakwaters, an almost entirely 𝗼𝗻-𝘀𝗶𝘁𝗲 𝗺𝗶𝘁𝗶𝗴𝗮𝘁𝗶𝗼𝗻 approach was possible. 

This cut in-lieu mitigation fees by about 80%, roughly USD 14 million, worth 15% of total project costs. 

Meanwhile, the structures reduce wave energy and erosion along the South Shore and support oysters, finfish, crabs, invertebrates, and harbor seals, ultimately producing cleaner waters for all. 

Learn more here.